Retention amount on the Acme Construction bill equals 10% of 1,200,000. How much is withheld as retention?

Enhance your knowledge of GASB and FASAB Standards. Study with multiple choice questions, hints, and detailed explanations. Prepare efficiently for your exam!

Multiple Choice

Retention amount on the Acme Construction bill equals 10% of 1,200,000. How much is withheld as retention?

Explanation:
This question tests applying a percent to a total to determine how much is withheld from a construction payment. Retention is the portion kept back to ensure performance, usually stated as a percentage of the billed amount. Here, 10% of 1,200,000 is calculated by multiplying 1,200,000 × 0.10, which equals 120,000. So, 120,000 is withheld as retention. The other amounts correspond to different percentages or to no retention at all, but only 10% of 1,200,000 yields 120,000.

This question tests applying a percent to a total to determine how much is withheld from a construction payment. Retention is the portion kept back to ensure performance, usually stated as a percentage of the billed amount. Here, 10% of 1,200,000 is calculated by multiplying 1,200,000 × 0.10, which equals 120,000. So, 120,000 is withheld as retention. The other amounts correspond to different percentages or to no retention at all, but only 10% of 1,200,000 yields 120,000.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy